Loading...
Loading...
Browse all stories on DeepNewz
VisitPrimary reason for Flamanville EPR operational delays in 2025?
Technical issues • 25%
Regulatory challenges • 25%
Supply chain disruptions • 25%
Other • 25%
EDF official announcements and French energy grid reports
France's EPR Nuclear Reactor at Flamanville Connected to Grid on December 21, 2024, After 12-Year Delay, Producing 1,630 Megawatts
Dec 21, 2024, 11:48 AM
The EPR nuclear reactor at Flamanville, France's most powerful reactor, has been connected to the national electricity grid as of December 21, 2024, after a lengthy construction period of 17 years and a delay of 12 years. The reactor, which is capable of producing 1,630 megawatts of low-carbon electricity, is expected to supply power equivalent to the consumption of approximately two million households at full capacity. The connection marks the first addition to France's nuclear fleet since the Civaux 2 reactor was brought online in 1999. Despite the delays and a total cost that ballooned to €13 billion, this milestone is seen as a significant achievement for the French nuclear industry. EDF, the operator, has indicated that the reactor will undergo a series of 10 to 15 stop-and-start operations in the next six months as it ramps up to full power.
View original story
Technical malfunction • 25%
Regulatory compliance issue • 25%
No significant issues • 25%
Other • 25%
Before end of 2025 • 25%
First half of 2026 • 25%
Second half of 2026 • 25%
Delayed beyond 2026 • 25%
On schedule • 25%
Delayed by up to 1 year • 25%
Delayed by more than 1 year • 25%
Cancelled • 25%
Less than 1% of national supply • 25%
1% to 2% of national supply • 25%
2% to 3% of national supply • 25%
More than 3% of national supply • 25%
Production issues • 25%
Funding issues • 25%
Regulatory issues • 25%
Other • 25%
Regulatory issues • 25%
Logistical challenges • 25%
Market demand fluctuations • 25%
Other • 25%
Weather conditions • 25%
Technical issues • 25%
Regulatory hurdles • 25%
Other • 25%
Funding issues • 25%
Supply chain problems • 25%
Regulatory hurdles • 25%
Other • 25%
No Delays • 25%
Minor Delays (up to 6 months) • 25%
Moderate Delays (6 months to 1 year) • 25%
Major Delays (more than 1 year) • 25%
Yes • 50%
No • 50%
1% to 2% • 25%
More than 3% • 25%
2% to 3% • 25%
Less than 1% • 25%